Home East County Photos: State Route 160/Highway 4 Connector Ramp Project

Photos: State Route 160/Highway 4 Connector Ramp Project

by ECT

On Friday, ECT visited the State Route 160/Highway 4 Connector Ramp Project with Ivan Ramirez, Engineering Manager for Contra Costa Transportation Authority.

According to Ramirez, a total of around 220 cement trucks will be needed when they begin to pour the concrete.

Although the project is currently slightly behind schedule due to environmental issues with birds laying nests, the project is still expected to be completed on time and under budget.

Here is more information on the project:

State Route 160/Highway 4 Direct Connector Ramps

The existing State Route 160/Highway 4 interchange currently includes only two of the four possible interchange movements: the eastbound Highway 4 to northbound State Route 160 connector ramp, and the southbound State Route 160 to westbound Highway 4 connector ramp. The State Route 160/Highway 4 Direct Connector Ramps project will construct two new connector ramps, one connecting westbound Highway 4 to northbound State Route 160, and one connecting southbound State Route 160 to eastbound Highway 4.

The project scope includes adding an additional 12-foot auxiliary lane to the outside of existing State Route 160 in both directions between the State Route 160/Highway 4 Interchange and the East 18th/Main Street Interchange, as well as building a soundwall extension and retaining walls. The southbound State Route 160/Highway 4 separation structure will accommodate a future eBART extension in the median of Highway 4.

PROJECT ALLOCATED BUDGET

The project is funded entirely by $50 million in Bridge Toll Funds.

SCHEDULE

Construction began in March 2014 and is expected to be complete in late 2015 or early 2016, weather depending

PROJECT UPDATE – March 2015

Milestone Activities:

  • Completion of southbound SR4/SR160 separation bridge over Highway 4 -Summer 2015

Recently Completed Work:

  • Completed falsework for the northbound SR 160 viaduct.
  • Began construction of the southbound SR 160 viaduct falsework
  • Imported 50% of soil needed for the project.

Upcoming Work:

  • Place deck concrete for southbound SR4/SR160 separation bridge over Highway 4.
  • Place concrete for the northbound SR 160 viaduct.